- Acquired the land: 2013 - 2014
- Public / stakeholder engagement and early design concepts: 2014 - 2016
- Preparation of planning application: 2016 - 2017
- Submission of planning application: July 2017
- Further design evolution: 2017 – 2018
- Submission of Addendum: October 2018
- Planning application determined: Q1 2019
- Work commences on site: Q2 2019
- First residents due to move in: 2022